Clairidge Way Storm Drain Improvement Project


Background
Last Updated: 6/19/2009
The Clairidge Way project area consists of approximately 34 acres of low-density residential neighborhood that drains to Chicken Ranch Slough. The project area is bounded by Oliveview Avenue to the north, Norris Avenue to the east, Montclaire Street to the west, and Robertson Avenue to the south.

The project will upgrade the drainage system, built in the late 1950's to late 1960’s to meet the current County standards.

The storm drain improvement project was approved by the Board of Supervisors and advertised for construction contractors on February 3, 2009. The public bid opening was March 12, 2009. There were 19 bids submitted. On March 23, 2009, the construction contract was awarded to the lowest bidder - Teichert Construction.
Description
Last Updated: 6/19/2009
The County of Sacramento Department of Water Resources is proposing the project to improve flood protection in your neighborhood.

New pipe will be installed in Robertson Avenue from 3741 Robertson Avenue to Norris Avenue. The new pipe will serve as a bypass and storage for the existing system. A new outfall structure at 3741 Robertson Avenue will connect the new pipe to Chicken Ranch Slough. In addition, the culvert in Clairidge Way will be upgraded.
Project Update
Last Updated: 10/21/2009
Project construction was completed on October 9, 2009. The neighborhood's cooperation and understanding during construction was greatly appreciated and assisted in making this a successful project.
Quality Control
Last Updated: 4/9/2009
Terry Darrough, Supervising Construction Inspector, is handling the administrative duties and major field issues. The inspector assigned to oversee construction is Hank Zablotny. He will resolve most field issues and ensure that the project construction meets the design specifications.

During construction, all efforts will be made to minimize residential impacts. Hank Zablotny will be available to address construction project issues and act as community liaison to the general public.
Tentative Schedule
Last Updated: 6/19/2009
  • Begin Construction - May 2009
  • End Construction - September 2009

For More Information...
Last Updated: 4/9/2009
Please contact:
Title Name Phone Email
Assoc. Civil Engineer  David Bolen  874-8645  bolend@saccounty.net 
Assistant Civil Engineer  Rohit Vasishta  874-8393  vasishtar@saccounty.net 
Teichert Construction, Project Manager  Francisco Guizar  386-5854  fguizar@teichert.com 
Construction Inspection Supervisor  Terry Darrough  875-2760  darrought@saccounty.net 
Senior Construction Inspector  Hank Zablotny  838-1365  zablotnyh@saccounty.net 