East Elk Grove Groundwater Treatment Plant

Photos

Project Description

This project involves construction of a new groundwater treatment plant and equipping of two supply wells in the East Elk Grove area north of the the intersection of Waterman Road and Grantline Road.  

Proposed facilities include:

  • Pressure filter treatment system
  • 3.5 MG water storage tank
  • Treated and backwash water pump stations
  • 0.25 MG backwash water storage tank
  • Backwash reclaim pump station
  • Sodium hypochlorite and sodium bisulfite feed and storage facilities
  • Soft water treatment system
  • Operations building

Project Snapshot

  • Contract time started on 3/26/01.
  • Estimated completion — Spring 2002
  • Overall cost — $7 million (without change orders)
  • The 24-inch Treated Water Main that provides water to the Suburban Propane tanks is in service. The Contractor has completed installation of the 20-inch raw water main that run down Waterman Road.
  • Contractor is proceeding with installation of onsite buried pipes.
  • Erection of the steel shell of the 3.5MG water storage tank is complete and coatings have begun. Erection of the 0.25MG backwash tank shell is under way.
  • The underslab plumbing and electrical services are being installed for the Control Building.
  • Offsite fabrication of the above ground steel pipe has begun.

Project Team Coordinators

 

Cost Summary — August 31, 2001

Base bid contract value

$6,789,000

Total work complete

$2,706,776

% Cost to date 39%
Contract change orders (approved) $0.00
% CCOs to total contract 0.00%
Retention amount $270,677.00

 

Time Summary — August 31, 2001

Contract award:

3/9/01
Working days started 3/26/01
Total working days 250
Original completion 3/24/02
Unworkable days 3/24/02
Time extension days 0
Revised required completion 3/24/02
RE estimated completion 3/24/02
Completion per Contractor's schedule 3/24/02
Substantial completion 
Field acceptance 
Working days to date 112
% Time elapsed 45%
 